Spring and early summer have been busy periods at the Railway History Center in Snoqualmie. Construction of the third phase – the Railway Education Center – is rapidly advancing, but Spike is a little behind posting photos. Plumbing and electrical has been run inside the foundation, the concrete floor has been poured, and now framing is underway. Here is a short gallery post incorporating some highlights of the floor construction. Spike will follow up in a few days with another gallery post that depicts framing progress.
An excavator filled inside the stem walls with a select fill. The
stem walls elevate the building above the flood plain. Grade
beams and utilities are located within the walls.
|
Plumbers and electricians ran pipe and conduit below what will
be the first floor. Pipe hangers will attach these pipes and
conduit to the bottom of the concrete floor.
|
The concrete crew pumped concrete into the
rebar cages.
|
A large concrete pump truck simplified the floor pour by
delivering concrete exactly where it was needed.
|
The concrete pumper allowed the crew to direct concrete around
the utility pipes in an efficient manner.
|
A simple 2×4 board was used to level the concrete.
|
Hand trowels helped smooth the surface.
|
A larger trowel helped make the floor surface uniform.
|
After the concrete cured slightly, workers performed
additional surfacing to create a really smooth surface.
|
A power trowel smooths the surface of the floor.
|
The complete foundation and first floor is ready for the
framing crew!
|