Spring and early summer have been busy periods at the Railway History Center in Snoqualmie. Construction of the third phase – the Railway Education Center – is rapidly advancing, but Spike is a little behind posting photos.  Plumbing and electrical has been run inside the foundation, the concrete floor has been poured, and now framing is underway.  Here is a short gallery post incorporating some highlights of the floor construction.  Spike will follow up in a few days with another gallery post that depicts framing progress.
| 
 
An excavator filled inside the stem walls with a select fill.  The  
stem walls elevate the building above the flood plain.  Grade  
beams and utilities are located within the walls. 
 | 
| 
 
Plumbers and electricians ran pipe and conduit below what will 
be the first floor. Pipe hangers will attach these pipes and  
conduit to the bottom of the concrete floor. 
 | 
| 
 
The concrete crew pumped concrete into the  
rebar cages. 
 | 
| 
 
A large concrete pump truck simplified the floor pour by 
delivering concrete exactly where it was needed. 
 | 
| 
 
The concrete pumper allowed the crew to direct concrete around 
the utility pipes in an efficient manner. 
 | 
| 
 
A simple 2×4 board was used to level the concrete. 
 | 
| 
 
Hand trowels helped smooth the surface. 
 | 
| 
 
A larger trowel helped make the floor surface uniform. 
 | 
| 
 
After the concrete cured slightly, workers performed  
additional surfacing to create a really smooth surface. 
 | 
| 
 
A power trowel smooths the surface of the floor. 
 | 
| 
 
The complete foundation and first floor is ready for the  
framing crew! 
 | 
				